Sprint delivery within 90 days
The challenge
Two delivery squads were completing approximately 33% of planned work. Competing priorities, inconsistent work readiness, and unclear ownership made execution difficult to predict.
What we changed
- Strengthened work-readiness standards
- Clarified cross-functional ownership
- Exposed risks and dependencies earlier
- Improved planning and release cadence
- Increased leadership visibility
The outcome
Sprint delivery increased to more than 80% within 90 days — a 47+ percentage-point improvement and approximately 2.4x the original delivery rate.